top of page

Method Statement for Site Mobilization




1.       Objective

The objective of this method statement is to define the procedures and responsibilities for the mobilization of the construction site in preparation for the commencement of construction activities.


2.       Scope

This method statement applies to all personnel involved in the site mobilization process, including the project manager, site manager, construction team and any other relevant parties.

 

3.       Responsibilities


3.1 Project Manager:

  • Planning and Coordination: Develop a comprehensive mobilization plan, including resource allocation, equipment procurement, and manpower requirements.

  • Budgeting: Ensure that the mobilization activities stay within budget constraints.

  • Client Communication: Keep the client informed about the mobilization progress and address any concerns or queries.

  • Contract Compliance: Ensure that the mobilization adheres to contractual agreements.


3.2 Project Engineer:

  • Design Coordination: Collaborate with the design team to ensure that design specifications align with mobilization requirements.

  • Resource Management: Oversee the procurement and mobilization of necessary materials, equipment, and tools.

  • Quality Assurance: Ensure that all mobilization activities meet quality standards and comply with project specifications.

  • Technical Problem Solving: Address any technical challenges that arise during mobilization.


3.3 Site Engineer:

  • On-site Supervision: Oversee the day-to-day activities on the construction site during mobilization.

  • Coordination: Collaborate with various teams, including subcontractors, to ensure smooth mobilization.

  • Documentation: Maintain accurate records of mobilization activities and report progress to the project manager.

  • Quality Control: Ensure that all work meets the required quality standards.


3.4 Safety Officer:

  • Safety Compliance: Implement and enforce safety protocols and regulations to prevent accidents during mobilization.

  • Training: Conduct safety training sessions for all personnel involved in mobilization.

  • Risk Assessment: Identify potential safety hazards and implement measures to mitigate risks.

  • Emergency Response Planning: Develop and communicate emergency response plans in case of accidents or incidents.


3.5 Foreman:

  • Workforce Management: Supervise and coordinate the activities of construction workers during mobilization.

  • Task Allocation: Assign specific tasks to workers and ensure they have the necessary resources and equipment.

  • Progress Monitoring: Keep track of the progress of mobilization activities and report to higher authorities.

  • Problem Resolution: Address any issues or challenges that arise on the site promptly.


4.       Procedures


4.1. Pre-Mobilization Planning

  • Conduct a site assessment to identify any potential hazards, environmental considerations, and logistical challenges.

  • Obtain all necessary permits, clearances, and approvals for mobilization activities.

  • Develop a site mobilization plan that includes timelines, resource requirements, and responsibilities.

  • Assemble a mobilization team with representatives from key departments, including project management, engineering, procurement, and safety.

  • Evaluate and finalize the construction site based on accessibility, proximity to resources, and alignment with project specifications.

  • Identify and procure necessary materials, equipment, and tools required for mobilization.

  • Plan logistics for the transportation of equipment, materials, and personnel to the construction site.

  • Ensure that the site is accessible and prepared for mobilization.

  • Provide training and orientation sessions for the project team to ensure everyone is familiar with the project goals, safety procedures, and their respective roles.

  • Conduct a kick-off meeting to brief the entire project team on the pre-mobilization plan, address any queries, and set expectations.

 

4.2. Establishment of Site Facilities

  • Establish temporary access roads for construction vehicles and equipment to ensure smooth movement on and off the site.

  • Set up temporary site offices, including necessary amenities such as electricity, water, and internet connectivity.

  • Arrange for temporary welfare facilities for workers, including restrooms, changing areas, and break areas.

  • Allocate space and establish storage areas for construction materials and equipment. Implement inventory management systems to track materials and equipment.

  • Implement safety measures, including signage, first aid stations, and emergency response plans.

  • Install clear and visible signage indicating safety protocols, restricted areas, and emergency exits.

  • Include directional signs for various site facilities.

 

4.3. Site Access and Security

  • Implement access control measures to ensure only authorized personnel and vehicles can enter the site.

  • Install temporary fencing and signage to demarcate the construction area and ensure public safety.

  • Secure the site against unauthorized entry and theft of materials and equipment.

  • Issue identification badges to authorized personnel, subcontractors, and visitors.

  • Establish a protocol for registering and tracking visitors.

  • All visitors should be accompanied by authorized personnel and undergo a brief orientation on site safety rules.

  • Implement a system for registering and tracking vehicles entering and leaving the construction site.

  • Ensure that only authorized vehicles are allowed access.

  • Install surveillance cameras at key points around the construction site, including entry and exit points, storage areas, and high-value assets.

  • Monitor the surveillance footage regularly and address any security concerns.

  • Ensure proper lighting throughout the construction site, especially at access points and perimeter fencing.

 

4.4. Material and Equipment Delivery

  • Coordinate the delivery of construction materials and equipment to the site according to the project schedule.

  • Inspect and document the condition of delivered materials and equipment to identify any damage or discrepancies.

  • Organize and store materials in designated areas to maintain order and facilitate easy access.

  • Maintain detailed records of each delivery, including packing lists, invoices, and inspection reports.

  • Document any discrepancies or damages and communicate with suppliers for resolution.

  • Notify relevant construction teams about the arrival of materials and equipment.

  • Coordinate the timely distribution of materials to different work areas as per the project plan.

 

4.5. Site Layout and Marking

  • Mark out the construction area based on approved drawings and specifications, clearly defining locations for structures, access routes, and storage areas.

  • Establish temporary access roads and parking areas for construction vehicles and personnel.

  • Install necessary temporary structures such as hoardings, site offices, and site welfare facilities according to the site layout plan.

  • Clearly mark the locations of underground utilities, including water, electricity, and telecommunication lines. Take precautions to avoid accidental damage to utilities during excavation.

 

5. Health and Safety

  • Conduct a safety induction for all personnel entering the site, emphasizing key safety rules, emergency procedures, and the proper use of personal protective equipment (PPE).

  • Implement safety measures to mitigate potential hazards, such as fall protection systems, hazard signage, and fire prevention measures.

  • Ensure that all construction activities comply with relevant health and safety regulations and standards.

 

6. Environmental Considerations

  • Implement measures to minimize environmental impact, such as erosion control, sedimentation management, and waste management practices.

  • Consider the conservation of natural resources and the preservation of existing flora and fauna during mobilization activities.

 

7. Communication and Coordination

  • Establish clear communication channels among project stakeholders, including construction teams, subcontractors, and suppliers.

  • Coordinate with local authorities, utility providers, and other relevant parties to ensure smooth mobilization activities and compliance with regulations.

 

8. Monitoring and Review

  • Conduct regular inspections and audits to monitor the progress of site mobilization activities and ensure compliance with the established procedures and safety standards.

  • Review the effectiveness of the site mobilization procedures and adjust as necessary based on feedback and lessons learned.

 

9. Record Keeping and Documentation

  • Maintain detailed records of all mobilization activities, including delivery receipts, site assessments, safety inspections, and any incidents or near misses.

  • Document any changes or deviations from the original mobilization plan, along with justifications and corrective actions taken.

 

10. Attachments

10.1 Site Mobilization Plan

10.2 Project Mobilization Schedule

10.3 Safety Checklist

10.4 Safety Risk Assessment


Disclaimer: The photographs displayed on this platform are informal and illustrative purpose only. All images are subject to copyright and intellectual property rights and belongs to the rightful owner.

61 views0 comments

Recent Posts

See All

Comments


bottom of page